section 278 lighting design

If a planning condition on your scheme mentions Section 278, there’s a good chance street lighting is hiding somewhere inside it. A new junction, a widened access, a moved crossing: change anything on the public highway and the lighting around it usually has to change too. That’s the territory of Section 278 lighting design, and it’s easy to underestimate. That’s also where programmes quietly start to slip.

This guide explains how Section 278 lighting design actually works across the UK, with the main focus on England and Wales and a section on Scotland and Northern Ireland. You’ll get what it is, the standards your designer works to, how approval runs, what a worked example looks like, and the mistakes that send drawings back for another round. It’s built from the current standards (as of October 2026) and from published guidance from a spread of highway authorities, so it reflects what councils are asking for now.

One caveat before we start. Every highway authority has its own specification and process. Use this as a map, then check the details with the authority you’re dealing with. And it isn’t legal advice.

What is Section 278 lighting design?

Section 278 of the Highways Act 1980 lets a highway authority agree with a developer that the developer will pay for, or carry out, works to the existing public highway, provided the authority is satisfied the works will benefit the public. Think roundabouts, priority junctions, signal-controlled junctions, right-turn lanes and better pedestrian and cycle facilities.

Section 278 lighting design is the lighting slice of that package. Someone has to decide which columns stay, which move, which get replaced and where new ones go. Then they have to prove, with calculations, that the finished road is lit to the right standard. Finally they produce the drawings, electrical design and schedules the authority needs to approve the scheme and, later, adopt it. In short, it’s highway lighting design done to the authority’s rules.

Two scope points are worth knowing:

  • Section 278 itself applies in England and Wales. Scotland and Northern Ireland use different road legislation with a similar logic (see the Scotland and Northern Ireland section below). The lighting standards are the same across the UK.
  • Who the authority is. For most roads it’s the local highway authority. For motorways and major A-roads it’s National Highways.

And yes, the agreement has teeth. If agreed payments aren’t made, the authority can direct that access to the site is stopped up. It’s not a formality.

When do you actually need Section 278 lighting design?

The simple test is whether your scheme touches a lit public highway. If it does, lighting needs a proper look. The usual triggers:

  • A new site access or bellmouth junction
  • A new or altered roundabout
  • Signalised junctions and new crossings
  • Widening, new footways or cycleways
  • Columns, illuminated signs or bollards that now sit in the wrong place

That last one catches people out. You might not be adding a single new light, but if the new kerb line puts an existing column in the middle of a footway, it has to move. And the authority will expect the replacement arrangement to maintain existing lighting levels. Some councils also require any new lighting to be switched on before the old units are disconnected and removed, so you can’t create a dark gap while works are going on.

Illuminated street furniture counts as well. Surrey’s guidance, for example, treats illuminated furniture as a lighting asset in its own right.

Section 278 vs Section 38: where lighting fits

People mix these up constantly, and the lighting rules differ slightly between them. Here’s how Section 278 lighting design compares with Section 38 lighting.

Section 278 Section 38
What it covers Works to the existing public highway New roads built by the developer and offered for adoption
Typical example Site access junction, roundabout, new crossing New estate roads
Lighting involved Alterations to existing lighting plus new units A complete new lighting scheme for the adoptable network
Outcome Works become part of the maintained highway after the maintenance period Roads and associated assets (drains, lighting, structures) adopted

Big developments often need both. In that case the lighting design for the estate roads and the off-site junction should be coordinated, ideally by the same designer, because the authority will review them together.

Scotland and Northern Ireland: what replaces Section 278

If your site is in Scotland or Northern Ireland, don’t write Section 278 on the drawings. The lighting design work is the same, because BS 5489-1, BS EN 13201 and the ILP guidance apply across the UK. What changes is the legal route and the paperwork.

Scotland. Works to an existing public road need the roads authority’s written consent under Section 56 of the Roads (Scotland) Act 1984. New roads go through Road Construction Consent under Section 21, and councils describe the two processes as similar. Some authorities spell out lighting requirements. Ayrshire Roads Alliance, for example, asks for a plan of existing street lighting (including illuminated signs) with a Section 56 application, and publishes a road lighting electrical installation certificate form and standard drawings. Check your council’s own guidance, and the National Roads Development Guide it points to.

Northern Ireland. Under the Roads (NI) Order 1993, anyone working on a public road needs consent from the Department for Infrastructure (DfI). For improvements required by a planning permission, DfI says consent is granted through one of two forms of agreement: an Article 3(4C) agreement or a licence agreement. Ask DfI Roads which applies to your scheme before your designer starts drafting.

The design, DNO and commissioning points in the rest of this guide carry over. Procedures and certificates will differ, so get the local requirements in writing early.

The standards behind Section 278 lighting design

Here’s the stack, roughly in order of importance for highway lighting design in the UK.

BS 5489-1:2020 is the British Standard code of practice for road lighting. It replaced the 2013 edition and was aligned with the BS EN 13201 series. It also added new guidance for lighting in smart city settings and where columns are co-located with EV charging points. It covers design strategy, risk assessment and classification, and practical considerations like column siting.

BS EN 13201 is the European series that actually defines the lighting classes and performance requirements. Part 1 is a technical report on selecting classes, Part 2 sets performance requirements, Part 3 covers calculation, Part 4 measurement, and Part 5 energy performance indicators. The 2015 revision is what most councils still cite.

Institution of Lighting Professionals (ILP) guidance fills in the rest. The ones that come up most on S278 work:

  • GN01:2021, reducing obtrusive light
  • GN08:2023, bats and artificial lighting (written with the Bat Conservation Trust)
  • PLG04, environmental lighting impact assessments
  • PLG23:2020, lighting for cycle infrastructure
  • PLG02, conflict areas on the highway (updated this year, see below)

Around these sit the supporting standards: BS 7671 for the electrical installation, BS EN 40 for columns, and BS EN 12767 for passive safety of support structures.

Then there’s the council’s own specification, and this is the one that wins arguments. Authorities set their own requirements for lanterns, colour temperature, dimming, column types and finishes, and they will check your design against them. A design that satisfies the British Standard but ignores the local spec will bounce.

What’s new in 2026

Two developments are worth knowing about.

  1. PLG02/26 landed in June 2026. The ILP published the updated Application of Conflict Areas on the Highway, replacing the 2013 edition. It tightens up what genuinely counts as a conflict area, gives guidance on picking the right C class, covers the five-second approach principle and glare limitation, and includes typical layouts for T-junctions, roundabouts and crossings. Since S278 schemes are mostly junctions and crossings, this one matters. Expect authorities to start referring to it.
  2. BS EN 13201 is being revised. A BSI draft for public comment of BS EN 13201-2 appeared in May 2026, and CEN drafts of Parts 2 and 3 carry a 2026 designation. As far as I could find, the 2015 text is still what applies to live submissions, but it’s worth asking your authority which edition they require, especially if your project runs into 2027.

How lighting classes get chosen for Section 278 lighting design

EN 13201-2 sorts lighting requirements into families:

  • M classes for roads with motorised traffic, measured in road surface luminance
  • C classes for conflict areas such as junctions, roundabouts and crossings, measured in illuminance
  • P classes for pedestrians, cyclists, residential streets and footways, also measured in illuminance

There are extra optional criteria too (hemispherical, vertical and semi-cylindrical illuminance) for places where seeing vertical surfaces or recognising faces matters.

Picking the class isn’t a lookup exercise. BS 5489-1:2020 sets out a design strategy and risk assessment approach, taking in things like speed, traffic volume, the mix of road users and how complex the layout is. Many councils shortcut this with a table linking road hierarchy to a lighting class, colour temperature and column height, so check whether yours does.

The common pitfall is over-designating conflict areas. Call every access a conflict area and you raise light levels everywhere without actually highlighting the real danger spots, which is exactly the confusion PLG02 was written to clear up. More light isn’t safer light, and it costs more to run.

Dimming is also part of the design these days. Many specifications require dimmable drivers connected to a central management system (CMS), and the dimming profile goes on the drawing. One published example from a county council specifies 50% dimming between 21:00 and 06:00. BS 5489-1 also allows light levels to be adjusted according to the spectral characteristics of the source (the S/P ratio), which is why you’ll see S/P ratios quoted in subsidiary road designs.

Beyond lux levels: the environmental side

A scheme can hit every number in EN 13201 and still get a hard time from the authority’s ecologist or the planning officer. Three things to design for from day one.

Obtrusive light. GN01:2021 sorts sites into environmental zones from E0 (protected dark areas) to E4 (bright urban), each with limits on light trespass into windows, sky glow, and upward light ratio. The upward light ratio cap runs from 0% in the darkest zones up to 15% in the brightest. Your designer should identify the zone early, because it caps what you can do.

Bats and wildlife. On sites near hedgerows, tree lines, watercourses or known commuting routes, follow GN08:2023. In practice that means no upward light, luminaires mounted level rather than tilted, back shields where needed, warmer colour temperatures, and keeping dark corridors dark.

Colour temperature. 3000K is the figure you’ll see most in council specifications, and some go lower depending on the site. Lincolnshire’s policy, for instance, allows 3000K or below depending on the brief.

Cyclists. If your scheme includes cycle infrastructure, PLG23 guidance applies, and several authorities ask you to agree the lighting approach with their street lighting engineer before you start designing.

The Section 278 lighting process, step by step

Details vary between authorities, but the skeleton is remarkably consistent. This is the usual route for Section 278 lighting design, from first survey to adoption.

  1. Get planning permission first. An S278 application usually can’t be processed until full or reserved matters permission is in place. Pre-application advice is often available and it’s worth using.
  2. Talk to the lighting team early. Lighting is often run by a separate team, or even a separate contractor, from the highways development team. Surrey, for example, has its lighting contractor check S278 lighting designs and expects them to install the approved lighting. Find out how your authority works before you appoint anyone.
  3. Appoint a competent designer. Councils want to see designers with recognised competence in road lighting. Ask about ILP membership and relevant experience with your authority.
  4. Survey and concept design. Establish what’s out there: existing columns, their condition, ownership, cable routes, signs and bollards. Lighting should be thought about at the same time as the street layout, not after it. It’s far cheaper to move a kerb line on a drawing than a column on site.
  5. Detailed design and submission. The designer produces calculations, layouts and electrical design (more on contents below).
  6. Technical approval. This is the back-and-forth stage. One London borough quotes roughly 5 to 12 weeks for technical approval, and that assumes your drawings are in decent shape. Road safety audits (typically Stages 1 and 2) are normally submitted alongside the design.
  7. Legal agreement. Once the design is approved, the legal agreement is drawn up. The authority’s legal team prepares the agreement, and its preconditions are normally satisfied before it is signed.
  8. Pre-start and road space. Work can only start once the design is approved, the agreement and warranties are completed, road space is booked and a pre-start meeting has taken place. Streetworks booking can need up to three months’ notice in some areas.
  9. Construction and inspection. The authority inspects as you build. Expect to be asked to prove installation as you go, not just at the end.
  10. Completion and maintenance period. After works are finished you submit as-built drawings and test certificates, a Stage 3 road safety audit is usually carried out, and the authority issues a certificate that starts the maintenance period, normally 12 months.
  11. Final inspection and adoption. At the end of the maintenance period the authority inspects, defects are put right and the works are adopted.

What goes in a Section 278 lighting design submission

Ask your authority for its checklist, because they differ, but this is what a typical package contains:

  • Lighting layout drawing (often at 1:500) showing existing and proposed columns, with the limit of works clearly marked
  • Uniquely numbered column positions, agreed with the authority
  • Lighting calculation reports, commonly produced in Lighting Reality, plus the electronic files
  • Lantern and column data sheets, including LED details, colour temperature and dimming profile
  • Column and bracket details, plus foundation design where required
  • Electrical design: cable routes and sizes, voltage drop and cable calculations, feeder pillar locations
  • A design risk assessment or checklist covering CDM 2015 duties
  • A schedule of existing apparatus to be removed, relocated or retained
  • Details of any affected illuminated signs and bollards

One point that trips people up: as-built drawings have to include the lighting. Surrey, among others, expects lighting information in the as-built submission before the S278 works are handed over, and all lighting equipment needs to be fully operational at adoption.

Worked example: lighting a new site access junction

This is an illustrative scenario, not a real project. The actual classes, spacings and requirements always come from the authority’s specification and brief.

Imagine a 120-home development on the edge of a market town. The planning permission requires a new priority junction onto a 30 mph distributor road, a pedestrian refuge crossing near the entrance and a short length of new footway. The road is already lit. Here’s how the Section 278 lighting design process typically unfolds.

Stage What happens What the authority wants to see
1. Survey The designer records every column, lantern, cable route, sign and feeder pillar around the works, and notes two existing columns that sit inside the new junction mouth. Condition, ownership and location of existing apparatus
2. Concept The designer decides which columns can stay, which must move and where new ones are needed to light the junction and the refuge. A layout showing existing and proposed columns, with the limit of works marked
3. Classification The main road keeps its existing lighting class. The junction and crossing are tested as possible conflict areas using PLG02/26. The new footway is assessed as a pedestrian area. The reasoning behind each class, traceable to the brief and the standards
4. Environmental check The designer identifies the GN01 environmental zone and checks for hedgerows, trees or watercourses that call for GN08 measures. Obtrusive light compliance and wildlife measures where relevant
5. Calculations Photometric calculations show the lit result meets the chosen classes, with the maintenance factor and surface assumptions stated. Calculation reports and electronic files in the required software
6. Electrical design Cable routes, voltage drop and protection are designed, the capacity of the existing feeder pillar is checked and a DNO application is prepared. Cable calculations, feeder pillar details and supply arrangements
7. Approval and build Technical approval, road safety audits, then construction. New columns are commissioned before the old ones come out. Approved drawings, inspection records and test certificates
8. Handover As-built drawings, test certificates and data sheets are submitted and the maintenance period begins. As-built lighting information and fully operational equipment

The calculations are the part most people picture, but the stages around them are where programmes tend to slip: a survey that turns up an unmarked cable, a debate about what counts as a conflict area, a DNO application made too late, or a first submission with information missing.

Who’s who on a Section 278 lighting project

Projects run more smoothly when everyone knows who owns which decision.

Role What they do
Developer (applicant) Funds and delivers the works under the agreement and signs the legal documents
Lighting designer Surveys, designs, runs the calculations and produces drawings and schedules
Highway authority street lighting engineer Checks the design against the authority’s specification, inspects the installation and recommends adoption
Highways development team Manages the Section 278 agreement, technical approval and overall process
Road safety auditor Independent audits, normally at design stage and again at completion
Distribution network operator (DNO) Provides the unmetered electricity connection
Contractor Installs the approved design and supplies test certificates and as-built records
Ecologist (where needed) Advises on bats, wildlife corridors and other environmental constraints

Section 278 lighting design: key facts at a glance

Question Short answer
What is it? The lighting design for works to the existing public highway agreed under Section 278 of the Highways Act 1980
Where does it apply? England and Wales. Scotland and Northern Ireland use different legislation
Who approves it? The local highway authority, or National Highways for motorways and major A-roads
Main standards BS 5489-1:2020, the BS EN 13201 series, ILP guidance and the authority’s own specification
Lighting classes M (motorised traffic, luminance), C (conflict areas, illuminance) and P (pedestrians and cyclists, illuminance)
Key deliverables Layout drawings, photometric calculations, electrical design, column and lantern data, design risk assessment
Electrical supply Unmetered supply arranged with the DNO
After construction As-built drawings, test certificates, a maintenance period (normally 12 months) and adoption
2026 developments ILP PLG02/26 on conflict areas and draft revisions of BS EN 13201

Section 278 lighting glossary

  • Section 278 (S278): the agreement under the Highways Act 1980 for works to the existing public highway, and the basis for Section 278 lighting design.
  • Section 38 (S38): the agreement for new roads that will be adopted by the highway authority.
  • Technical approval: the authority’s formal sign-off of the design before work starts.
  • Road safety audit (RSA): an independent safety review. Stages 1 and 2 happen at design, Stage 3 at completion.
  • Column: the pole that supports a lantern.
  • Lantern (luminaire): the light fitting, including its optics and control gear.
  • Luminance: the light reflected from the road surface towards the driver, measured in cd/m².
  • Illuminance: the light falling on a surface, measured in lux.
  • Conflict area: a place where road users’ paths cross, such as a junction, roundabout or crossing.
  • S/P ratio: the ratio of scotopic to photopic light output of a source, used in some designs to adjust light levels.
  • Upward light ratio (ULR): the share of a luminaire’s light that goes above the horizontal.
  • CMS: central management system for remote control and dimming of street lighting.
  • DNO: the distribution network operator that owns the local electricity network.
  • Unmetered supply: an electricity supply billed on an agreed inventory rather than a meter, commonly used for street lighting.
  • ICP: an accredited independent connection provider that can carry out some connection work.
  • CDM 2015: the Construction (Design and Management) Regulations, which place design risk duties on designers.
  • As-built drawings: the record of what was actually installed.
  • Maintenance period: the period after completion, normally 12 months, when the developer remains responsible for defects.
  • Adoption: the point at which the highway authority takes over responsibility for the works.

Electrical connections for S278 street lighting

This is the stage that sneaks up on programmes, and S278 street lighting is no exception. New street lighting is normally an unmetered supply, and the developer has to arrange the connection separately with the local distribution network operator (DNO). The DNO or its contractor issues a certificate for the unmetered supply, which you pass to an electricity supplier, and you’re responsible for making sure the supply inventory is updated.

Some connection work is contestable, meaning an accredited independent connection provider (ICP) can do it. But ICPs usually have to get their designs approved by the DNO first, which adds time. DNOs publish their own timescales for unmetered works and they vary with the size and nature of the scheme. So make the application early rather than when the columns are already standing.

Commissioning, maintenance period and adoption

At handover the authority will typically want test certificates, as-built drawings with the final column numbering, column and lantern data, and evidence that the installation is complete and operational. Cumbria’s spec for S38 lighting, for instance, asks for as-built drawings, test certificates and data sheets as part of adoption.

During the maintenance period you stay responsible for faults and defects. Plan for it: a lighting outage that sits unreported for three months in year one is the sort of thing that delays the final certificate.

If you have a defects period under the building contract, line it up with the highway maintenance period. Buyers’ and tenants’ solicitors will ask for certificates confirming the works are in maintenance or adopted, so keep them somewhere findable.

Section 278 lighting design mistakes that slow approval

These come up again and again in council guidance and checklists.

  • Designing to the standard but not the local spec. Always get the authority’s current specification first.
  • Leaving lighting until the highway layout is frozen. Column positions fight with visibility splays, utilities, trees and driveways. Resolve the conflicts on paper.
  • Over-classifying conflict areas. More light, more cost, and a harder conversation with the environmental team.
  • Forgetting the small stuff. Illuminated signs, bollards and crossing beacons are easy to miss and awkward to add later.
  • Skipping the DNO until late. Connections take time and you can’t energise without them.
  • Removing old lighting before the new is live. Some authorities forbid it outright.
  • Incomplete as-builts. No lighting data, no handover.
  • Poor first submissions. Missing calculations, wrong file formats or unnumbered columns cost you a full review round.

Choosing a Section 278 lighting designer

Skip the generic checklist and ask a few pointed questions:

  • Have they got through technical approval with your authority before?
  • Do they run calculations in the software the authority expects?
  • Can they cover the electrical design and cable calculations, not just the photometrics?
  • Will they handle environmental constraints like bats and obtrusive light, or does that need a second consultant?
  • Do they understand conflict areas properly, including the new PLG02/26?

A designer who knows the council’s spec by heart is worth more than one with a nicer brochure.

Frequently asked questions

Do I need a Section 278 lighting design if I’m not adding new street lights?

Often yes. If your works affect existing columns, signs or bollards, the authority will want to see how lighting is retained or reinstated, with calculations to show levels are maintained.

Who pays for Section 278 lighting?

The developer. Under the agreement they fund and deliver the design and installation, and in many cases they also cover the energy used until the lighting is adopted. The highway authority checks, inspects and eventually adopts the works.

How long does Section 278 lighting design approval take?

It varies. One London borough quotes about 5 to 12 weeks for technical approval, but complex schemes, resubmissions and extra consents (such as traffic regulation orders) add time. Build contingency into the programme.

Can I use my own Section 278 lighting designer?

Usually, yes, subject to the authority checking and approving the design. Some authorities strongly prefer or require their own contractor to design or install, so confirm before you appoint.

Does Section 278 street lighting have to be LED?

In practice, yes. Current council specifications overwhelmingly call for LED, often with dimming and CMS connectivity, and many set the colour temperature at 3000K or lower.

Is Section 278 the same in Scotland and Northern Ireland?

No. Section 278 applies to England and Wales. Scotland uses the Roads (Scotland) Act 1984, mainly Section 56 for works to existing roads, and Northern Ireland uses the Roads (NI) Order 1993 through DfI. The lighting design standards are the same either way.

Which standards changed in 2026?

The ILP issued PLG02/26 on conflict areas in June, and draft revisions of BS EN 13201 were circulating for comment. BS 5489-1:2020 remains the current British Standard code of practice.

The short version

Good Section 278 lighting design is mostly about timing and homework. Find out who owns lighting at your authority, get their spec before you draw anything, design lighting alongside the highway layout, apply for the electrical connection early, and send in a complete first submission. Do those five things and most of the common delays simply don’t happen.

If you’re planning a scheme and want a second pair of eyes on the lighting side, get in touch before the highway layout is fixed. It’s the cheapest time to change your mind.

Sources and further reading

  • Highways Act 1980, Section 278 (legislation.gov.uk)
  • BSI: BS 5489-1:2020, Design of road lighting, and the BS EN 13201 series
  • Institution of Lighting Professionals: PLG02/26 Application of Conflict Areas on the Highway; GN01:2021; GN08:2023 (with the Bat Conservation Trust)
  • Published S278 and S38 guidance from Surrey, Central Bedfordshire, Herefordshire, Bristol, Havering, Solihull, Leicestershire, Wokingham, Medway, Gloucestershire and Shropshire councils
  • Council street lighting specifications from Lincolnshire, Wirral and Cumbria
  • DNO and council guidance on unmetered electricity connections; Roads (Scotland) Act 1984, Section 56; Ayrshire Roads Alliance and Renfrewshire Council road consent guidance; Department for Infrastructure (NI), Article 3(4C) and licence agreements guidance